ON
GOING PROJECTS
Implementation
of Sericulture Extension & Development Work Plan(2008-2011):
| 1. |
Project Title |
: |
Implementation of Sericulture
Extension & Development Work Plan. |
| 2. |
(a) Sponsoring Ministry/Division |
: |
Ministry of Textile's
& Jute. |
| (b) Executing Agency |
: |
Bangladesh Sericulture
Board. |
| 3. |
Bangladesh
Sericulture Board took the said Development project
under caption above with an estimated cost of Tk.
1216.00 lakh. As tenwards the project cost and time of the project have been increased to Tk. 1250.54 lakh and July'2011 respectively. The objectives of this project are
as follows:-
-
To extend and develop the
Sericulture through direct participation of
Govt., Private Organizations and NGOs;.
-
To establish sound relationship
between Govt. organizations and NGOs;
-
To suport financial help
to the persons involved in Sericulture, production
of cocoons and Silk yarn;
-
To arrange wide-range training
programe for the persons involved in Sericulture
profession to develop their technical efficiency;
-
To create employment facility
for the women;
-
To introduce ‘Chawki Rearing
system’;
-
To increase empowerment
of the rural poventy-stricken women enhancing
their income and genarating more employment
facility through sericulture activities; and
-
To create circumference
of social security, etc.
|
| 4. |
Location
of the project
Upazila/ District
(Attach map, where necessary) |
: |
Place
All over Bangladesh.
(The detail distribution of different establishments
and location of the project activities are shown
in Enclosure-I). |
|
5. |
a)
Cost of the Project
(In Lakh Taka) |
: |
-
Total : 1250.54
-
GOB : 1250.54
-
P.A. : - |
| b) Exchange rate
with date |
: |
Not applicable. |
|
6. |
Mode of Financing
with source |
: |
(In
LakhTaka) |
| Mode of financing |
GOB (FE) |
PA (RPA) |
PA source |
| Loan/credit |
- |
- |
- |
| Grant |
1250.54 |
- |
|
| Equity |
- |
- |
- |
| Others (specify) |
- |
- |
- |
|
| 7. |
Project
Implementation Period |
: |
-
Date of commencement: July’2008
-
Date of completion: June’2011.
|
The project
period was 2008-2010 and estimated cost was 1216.00
Tk. lakh. In the financial year 2008-09, the works amounting
Tk. 294.00 lakh were done against the allocated amount
of Tk. 300.00 lakh and the rest amount of Tk. 6.00 lakh
was deposited to the Govt. Treasury In the financial
year 2009-10 upto January 10, Tk. 450.00 lakh was released
against the ADP allocation of Tk. 900.00 lakh and upto
this time Tk. 349.33 lakh was spent against the various
activities of the project. Since the inception of the
project upto April, 11 cumulative expenditure is Tk.1076.42
lakh and physical & financial achievement of the
project is 86.07%. By this time due to increase of prices
of various materials and due to less amount of release
of fund in the first year of the project it was felt
to be revised.In this regard a meeting of DPEC held
on 02/02/10. In this meeting project cost and time of
the project have been revised and increased to Tk. 1250.54
lakh and June’2011 respectively.
The Achievement in the main components of
this project are as follows (from July/08 to June/11):
a) Production of mulberry saplings- 15.00 lakh
Nos.
b) Production & distribution of mulberry saplings-
15.00 lakh nos.
c) Production of Disease-Free-Layings- 9.69 lakh
Nos.
d) Production of Cocoons-3.70 lakh Kgs.
e) Production of silk yarn 2730 Kgs.
f) Improved chaki polu in being distributed
g) Establishment of exhibition plots of mulberry
cultivation has been completed, as per plan
h) Impart training to the seri-farmers -1520
persons.
i ) Employment gerenation is being increased
among the poor section of the socity through sericulture
profession.
Back
to Top
Sericulture
Extension Programme for the Chittagong Hill Districts
(2nd Phase).
| 1. |
Project Title |
: |
Sericulture Extension
Programme for the Chittagong Hill Districts (2nd
Phase). |
| 2. |
(a) Sponsoring Ministry/Division |
: |
Ministry of Chittagong
Hill Tracts Affairs & Ministry of Textile
& Jute. |
| (b) Executing Agency |
: |
Bangladesh Sericulture
Board (BSB). |
| 3. |
Objectives of the
Project
(Please specify)
-
To extend the sericulture activities in
the new prospective areas of the three hill
districts in a compact form with the help
of NGO' keeping the existing extension areas
intact.
-
To establish mulberry demonstration plot-cum
chawki rearing centres in the Sericulture
extension areas with a view to involve the
people in sericulture occupation through motivation.
-
To create employment of the poor tribal
and non-tribal people of the hill districts
and to reduce their poverty through extension
of sericulture,
-
To gear up the socio-economic condition
of the hard-core poor people through enhancing
the women participation in the field.
-
To impart training on rearing of silk worm,
cocoon production and reeling of silk yarn
to the people willing to take up sericulture
as a subsidiary occupation.
-
To reduce depending tendency of the people
on Government financial help and to make them
self sufficient through the sericulture activities.
|
|
4. |
Location of the project |
Location of the Project are as follow : |
| Name of
Office |
Place |
District |
Upozila |
Number |
| Regional Office (1) |
Rangamati |
Rangamati |
Rangamati Sadar |
1 |
| Center
Office (3) |
Rangamati |
Rangamati |
Rangamati Sadar |
3 |
| Khagrachari |
Khagrachari |
Khagrachari Sadar |
| Lama |
Bandarban |
Lama |
|
Sub Center Office (12) |
Rangamati Sadar |
Rangamati |
Rangamati Sadar |
12 |
| Longadu |
Rangamati |
Longadu |
| Betbonia |
Rangamati |
Kaukhali |
| Kaukhali |
Rangamati |
Kaukhali |
| Khagrachari Sadar |
Khagrachari |
Khagrachari Sadar |
| Matiranga |
Khagrachari |
Matiranga Sadar |
| Manikchari |
Khagrachari |
Manikchari |
| Panchari |
Khagrachari |
Panchari |
| Lama |
Bandarban |
Lama |
| Rupashipara |
Bandarban |
Lama |
| Raicha |
Bandarban |
Bandarban Sadar |
| AliKadam |
Bandarban |
AliKadam |
|
|
5. |
a)
Estimated Cost of the Project
(In Lakh Taka) |
: |
-
Total : 269.59
-
GOB : 269.59
-
P.A.(R.P.A) : -
-
Others : -
|
| b) Exchange
rate with date |
: |
Not applicable. |
|
6. |
Mode of Financing
with source |
: |
(In
LakhTaka) |
| Mode of financing |
GOB (FE) |
PA (RPA) |
PA source |
| Loan/credit |
- |
- |
- |
| Grant |
269.59 |
- |
- |
| Equity |
- |
- |
- |
| Others (specify) |
- |
- |
- |
| Total= |
269.59 |
- |
- |
|
| 7. |
Project
Implementation Period |
: |
-
Date of commencement: July’2008
-
Date of completion: June’2011.
|
The Achievement in the main components of
this project are as follows (from July/08 to April/11):
Back
to Top
Extension and Development of Sericulture in Public and
Private sector in Bangladesh.
| 1. |
Project
Title |
: |
Extension
and Development of Sericulture in Public and Private
sector in Bangladesh. |
|
2. |
a)
Sponsoring Ministry/ Division |
: |
Ministry
of Textile's & Jute. |
| b)
Executing Agency |
|
|
|
i) Lead Agency |
: |
Bangladesh
Sericulture Board (BSB) |
|
ii) Other agencies/
Organization |
: |
Bangladesh
Sericulture Research and Training Institute (BSRTI); |
| : |
Bangladesh
Silk Foundation (BSF). |
A project
under the caption ‘Extension and Development of Sericulture
in public and private sector in Bangladesh (2009-2014)’
is going on. Estimated cost
of this project is Tk.3000.00 lakh.It is being implemented
with joint collaboration of 3 nos.public and private
organizations.
The objectives of the above project are as
follows:-
| (a) |
To create employment facility
of 50 thousand people: |
| (b) |
To produce 45 thousand kgs. seed cocoons; |
| (c) |
To take lease 140 bighas land; |
| (d) |
To establish 5 Nos. ‘Chawki Rearing
centres’; |
| (e) |
To establish 23 Nos-‘Reshom polly’(Sericulture
village); |
| (f) |
Production and supply of 15.00 lakh
Nos, mulberry saplings/cuttings and 31.15 lakh Nos.
Disease Free Layings; |
| (g) |
To impart training in the country
on various Segment of Sericulture to 3640 persons
involved in various activities of Sericulture; |
| (h) |
To arrange foreign training and study
Tour for 39 Nos. Junior/Senior Executive officers; |
| (i) |
To provide Boshnies/Sericulture Farmers
with grant; |
| (j) |
To produce cocoons; |
| k) |
To
execute costruction works and conduct other allied
activities; |
| (l) |
Acquisition of land etc. |
The Achievement in the main components of
this project are as follows (from July/09 to April/11):
a) Production and distribution of mulberry
saplings- 4.00 lakh Nos.
b) Production and distribution of Disease-Free-Layings-
4.49 lakh Nos.
c) Production of Cocoons-1.10 lakh Kgs.
d) Production of silk yarn- 1350.700 Kgs.
e) Improved Chaki polu distribution is being
done as per requirment of the Rearers.
f) Establishment of "Chaki Rearing centres"
and "Resom polly" have been completed as per
plan.
g) Impart training to the seri-farmers -1456
persons.
|